Progress is now becoming noticeable for the paying public. 2 No lifts in the Western Subway have been commissioned and brought into use. Power supplies are derived from Switchroom LVS06 and run to local lift motor rooms. The TOC accommodation building on Platforms 6/8 has been commissioned and is occupied by NR staff. The Selux fittings for the platforms have delivered and commissioning of the lighting on the platforms should commence in October.

July 2007 - August 2010
£6.2M